open
S H

Task 27

Added by Suenaga Aya about 22 hours ago. Updated about 22 hours ago.

Status:
New
Priority:
Normal
Target version:
Start Date:
11/08/2024
Due date:
11/12/2024 (Due in 12 days)
Actual Start Date:
Actual Due Date:
% Done:

0%

Estimated time:
6:00 h
Remaining Estimate:
6:00 h
comment:
difficulty:
3
point:
1
difficulty:
3
point:
1
Category2
comment:


Add

Create child issues from issue set


Add

Subtasks


Add

Related issues 2 (2 open0 closed)

Follows Administrative application development (Critical Path) - Bug #7: Task 24NewOhashi Hiroyuki11/06/202411/07/2024

Delete relationActions
Precedes Administrative application development (Critical Path) - Bug #9: Task 30NewKawana Mari11/13/202411/15/2024

Delete relationActions

No data to display